4-story project in Jeff Park hits roadblock; commission fails to endorse plan
by BRIAN NADIG
The Community Development Commission at its Aug. 11 meeting refused to endorse a four-story redevelopment project for the vacant lots at Lawrence and Laramie avenues, a move that is expected to delay the project and possibly make it not economically feasible for the developer
Alderman John Arena (45th) has said that any delays in the project could place its feasibility in jeopardy because it needs to be approved by the City Council prior to new rules on affordable housing taking place on Oct. 13. Under the city’s current program, the project’s developer, the Mega Group, would have to contribute $400,000 to the city’s affordable housing fund but after Oct. 13, the amount would be $500,000.
Delays could force the lots to be vacant for several more years, according to Arena.
The commission’s vote came as a surprise, as the commission routinely approves projects which have been endorsed by the city Department of Planning and Development and the local alderman. The department was seeking the commission’s approval to enter a negotiated sale of the property to Mega and to advertise for alternative proposals.
At issue is the city’s plan to sell the lots which the city purchased through eminent domain for $1.46 million in 2006 for $1 to Mega. At one time Mega had agreed to reimburse the city for all of its acquisition costs, but the deal fell through after Mega could not obtain a zoning change to allow for a 132-condominium complex in the 5100 to 5300 blocks of West Lawrence Avenue.
A Mega official told the commission that the company would be unable to obtain financing for the $16 million project without the city giving it the property.
In addition, a city planning official told the commission that selling the parcels for $1 was appropriate because Mega had held up its end of the agreement 10 years ago. At the city’s urging, Mega purchased several buildings for the 132-unit project and tore the buildings down. Several of those properties purchased by Mega are now used as gravel parking lots.
The city-owned portion of the site has been appraised at $530,000, and it makes up about half of the land which would be developed for the current project. Plans call for 39 apartments and several storefronts for the vacant lots to the east of the Sportif Importer bike shop, 5225 W. Lawrence Ave.
Arena has said that the project is a good fit for the community because the site would be developed under the site’s existing zoning, B3-2, and the proposed four-story height is reasonable compared to the planned 10-story height in 2006. The project would serve as a gateway to the Jefferson Park business district and hep attract additional development to the area, according to Arena.
Weekly Digital Edition
Read every story. Skip every pop-up.
Get the full weekly edition delivered to your inbox — no interruptions, no waiting. Just local news the way it was meant to be read.
This is just part of today’s coverage. Get the full story - every article, every ad, every page. Subscribe now.
The Latest From Our Community
by BRIAN NADIG About a dozen smash-and-grab-style commercial burglaries in Edgebrook, Jefferson Park and Portage Park were reported to have occurred early Wednesday morning, Oct. 14, in the 16th (Jefferson read story
by BRIAN NADIG At least nine smash-and-grab-style commercial burglaries in Edgebrook, Jefferson Park and Portage Park were reported to have occurred early Wednesday morning, Oct. 14, in the 16th (Jefferson read story
by BRIAN NADIG Violent offenses reportedly are down 34 percent on the CTA from a year ago as the agency targets a section of the Red Line where criminals are read story
Two men reported that a man fired shots at them at about 12:15 a.m. Sunday, Oct. 11, in the 5300 block of West Berteau Avenue, according to 16th (Jefferson Park) District police. A 25-year-old man reported that read story
The second annual “Sip and Shop” in “Jeff West” will start at 11 a.m. Saturday, Oct. 17, running along Lawrence Avenue from Austin Avenue on the west and Major Avenue read story
Browse by Category
Weekly Digital Edition
Read every story.
Skip every pop-up.
No pop-up ads — ever. Just stories, the way they were meant to be read
Full weekly edition delivered to your inbox every week — no waiting, no missing issues
Support local journalism and help keep our community connected
Only $19.50/year
That's less than 38¢ a week
Purchase Digital Subscription
Paypal
$19.50
/year
You can submit your payment via Paypal with a Credit Card. You DO NOT NEED TO HAVE A PAYPAL ACCOUNT.. Just click the “Paypal Subscribe” button below to iniate your secure payment! You will be directed to a Secure Paypal page in which you can pay with a Paypal account if you have one, or you can select "Pay with Debit or Credit Cardt" option below and process your payment via credit card.
Venmo
$19.50
/year
You can submit payment of $19.50 for a 1 year subscription to Nadig Newspapers' Venmo account using this link. Please include the email address in the comment/note section that you would like the digital subscription sent to.