Entire stop work order lifted for Six Corners Sears redevelopment project, as fifth-floor beams installed without permit can remain following structural review 

by BRIAN NADIG

The stop work order issued in August for the Sears at Six Corners redevelopment project was completely lifted last month, clearing the way for  work on the fifth-floor addition to start up again.

It has been determined the installation of steel beams that was done without a construction permit on the fifth floor is “proper” and will not have to be removed and reinstalled, according to the city Department of Buildings. 

Some work had already been allowed to restart in the fall following the issuance of a stop work order on Aug. 23. At the time no permit had been issued for the construction of the planned 206-unit apartment building and  ground-floor Target department store.

The buildings department had been working with a structural engineering company to review the work which developer Novak Construction and its subcontractors had performed without a permit, which was eventually issued on Nov. 30. The steel beams were the last of the work that needed to be reviewed to ensure that all safety and other technical requirements of the building code were met.

The cost of the structural company’s review is being paid for by Novak, according to the department.

A portion of the former Sears building is being reused as part of the redevelopment project. The store has opened opened in 1938 and closed in 2018.

A stop work order also was issued while some of the former store was being demolished due to a permit issue.

Digital Edition No Pop-Ups

Weekly Digital Edition

Read every story. Skip every pop-up.

Get the full weekly edition delivered to your inbox — no interruptions, no waiting. Just local news the way it was meant to be read.

Only $19.50/year — less than 38¢ a week Subscribe Now

This is just part of today’s coverage. Get the full story - every article, every ad, every page. Subscribe now.

The Latest From Our Community

 





Photo by SumUp No Pop-Ups

Weekly Digital Edition

Read every story.
Skip every pop-up.

No pop-up ads — ever. Just stories, the way they were meant to be read

Full weekly edition delivered to your inbox every week — no waiting, no missing issues

Support local journalism and help keep our community connected

Only $19.50/year

That's less than 38¢ a week

Purchase Digital Subscription

Paypal

$19.50

/year

You can submit your payment via Paypal with a Credit Card. You DO NOT NEED TO HAVE A PAYPAL ACCOUNT.. Just click the “Paypal Subscribe” button below to iniate your secure payment! You will be directed to a Secure Paypal page in which you can pay with a Paypal account if you have one, or you can select "Pay with Debit or Credit Cardt" option below and process your payment via credit card.

Venmo

$19.50

/year

You can submit payment of $19.50 for a 1 year subscription to Nadig Newspapers' Venmo account using this link. Please include the email address in the comment/note section that you would like the digital subscription sent to.